The railway bridge at Wallington Station will be repainted in
January after a campaign by your local councillors Monica Coleman, Colin Hall
and Jayne McCoy
In order for the work to be carried out safely the council needs
to introduce a temporary way for traffic and pedestrians to move under the
railway bridge at the junction with Manor Road and Woodcote Road.
The Temporary Traffic Management
Order will come into effect on Monday 14 January 2013 with works taking place
at night between the hours of 10.00 p.m. and 5.00 a.m. It is expected that the
works will be finished by 25 February 2013. However, the Order will remain in force for 18
months to be re-introduced should further works be required.
When the works are taking place and the appropriate traffic signs
are displayed the Order will close certain lengths of pavements in Manor Road
and Woodcote Road on the approach to the bridge. The pavements will only be
closed one side at a time depending on which side of the bridge is being worked
on.
1 comment:
Excellent news :)
Post a Comment